Commissioning Sequence for Solar PV Plants

The order of commissioning from mechanical completion to commercial operation, the hold points between stages, and the U.S. documents behind each step.

Published November 13, 2026 · Vinicius Rafael Palaveri Leoni · 17 pages, PDF
Download the PDF

Why it matters

A commissioning test done in the wrong order can damage equipment, hide a defect or put people at risk. A test left out is usually found later, as a trip, a fire or an energy shortfall.

Most guidance describes individual tests. This paper covers what sits between them: the order, the dependencies, the hold points where one party hands the plant to another, and the records that show the plant was ready at each step. It is the opening paper of a series; each test has, or will have, its own guide.

Key figures from the example

4stages, from readiness to performance verification
3hold points, each a written release
16tests in the example plan: 11 cold, 5 hot
100%of strings and circuits covered by each record

Example: an anonymized 2.5 MWac fixed-tilt PV plant with 197 strings and 10 string inverters.

What the document covers

Who it is for

Commissioning engineers, EPC project managers, owner’s engineers and asset managers who plan, witness or review commissioning.

Reference standards

ANSI/NETA ATS-2025 and ECS-2024, IEC 62446-1, NFPA 70 (NEC), NFPA 70E, IEEE Std 1547 and 1547.1, IEEE Std 2800 and 2800.2, UL 1741.

Read the full document
Free to download. No sign-up required.
Download the PDF
Educational content. This document describes a method and illustrates it with an example. It is not an engineering study, design or recommendation for any specific project. Solstice Energy does not provide services that require professional engineering licensure in the United States. Site-specific studies must be prepared, signed and sealed by a licensed Professional Engineer.

Questions or comments on this document? Contact us.