Medium-Voltage Cable Acceptance Testing

How new medium-voltage cable systems are tested before first energization: shield continuity, insulation resistance and a VLF withstand test.

Published November 13, 2026 · Vinicius Rafael Palaveri Leoni · 16 pages, PDF
Download the PDF

Why it matters

The medium-voltage cables of a PV plant carry its entire output. They are few, they are buried, and a failure takes the plant or a large block of it out of service for days.

Factory tests say nothing about what happened to the cable afterwards: pulling damage, a nicked insulation shield, a void in a field-made termination. The acceptance test is the only check of the installed cable system as a whole, and insulation resistance alone is not enough to find those defects.

Key figures from the example

0.1 Hzsinusoidal VLF test frequency
21 kV rmsacceptance voltage, 15 kV class cable
60 minrecommended duration for a new circuit
10conductors tested in the example, including the spare

Example: the medium-voltage circuits of an anonymized 2.5 MWac PV plant. The example shows the test plan, not test results.

What the document covers

Who it is for

Commissioning engineers, testing technicians, EPC project managers and owner’s engineers who specify, perform or review cable acceptance tests.

Reference standards

ANSI/NETA ATS-2025, IEEE Std 400-2023, IEEE Std 400.2-2024, IEEE Std 400.3, ICEA S-94-649 and S-97-682, NFPA 70E.

Read the full document
Free to download. No sign-up required.
Download the PDF
Educational content. This document describes a method and illustrates it with an example. It is not an engineering study, design or recommendation for any specific project. Solstice Energy does not provide services that require professional engineering licensure in the United States. Site-specific studies must be prepared, signed and sealed by a licensed Professional Engineer.

Questions or comments on this document? Contact us.